In September 2025, Shelburne council awarded a $65,000 contract to ASBB Economics and Research to complete a market gap and investment readiness analysis for two municipally owned parcels along Highway 103. The project was meant to answer a practical question: what should go on that land, and what does the municipality need to do to make it attractive to developers. Nine months later, with the project's public completion date pushed to the end of July 2026, it's worth looking back at how that timeline was set, how it was communicated, and how far it has moved since.
At a glance |
The Highway 103 analysis was awarded in September 2025, discussed as a roughly spring 2026 deliverable at kickoff, and is now publicly listed for completion at the end of July 2026. The central question is not whether the work is deficient, but why the timeline moved so substantially without a clear public explanation. |
Date or period | What happened |
July 4, 2025 | Request for Proposal issued. |
August 6, 2025 | RFP closed after seven firms submitted proposals. |
September 2025 | Shelburne council awarded ASBB Economics and Research the $65,000 contract. |
October 14, 2025 | Kickoff meeting discussed a schedule ranging from roughly 18 to 26 weeks, with March raised as an informal target. |
End of July 2026 | The municipality’s public project page now lists anticipated completion. |
How the process started
The Request for Proposal went out on July 4, 2025, with a closing date of August 6. Seven firms submitted proposals. The municipality scored each one on four criteria: understanding and methodology, qualifications and experience, timeline, and budget. Timeline carried a 30 percent weight, tied with qualifications and experience as the heaviest single factor in the decision, and worth half again as much as budget.
ASBB was not the cheapest bid. Its proposal scored 12.4 percent on budget, well behind Turner Drake & Partners, which came close to a perfect score in that category. ASBB won on the strength of its combined methodology and experience scoring, finishing at 84.4 percent overall, about six points ahead of the next closest firm. That is a reasonably clear margin, and there's no real story in price alone here. The interesting part is what happened to the timeline that helped ASBB win.
What the RFP actually asked for
The RFP itself did not set a hard deadline. Instead, it asked each proponent to "provide a clear timeline, with scope of work milestones and completion date for all deliverables," and let that submitted timeline become part of the competitive score. In effect, the municipality was buying a promise about pace as well as a promise about the work itself.
The deliverables tied to that promise were specific. ASBB was contracted to produce a market gap assessment built around the two Highway 103 parcels by PID number, a commercial opportunity profile prioritizing at least five development options for those same parcels, an investment attraction package naming at least ten potential investors, and two presentations to the Economic Growth Committee, one at the midpoint and one at the end.
The payment structure is worth flagging too. Half the fee is paid at signing, before any deliverable exists, with the remaining half split evenly between a mid-point review and the final presentation. Payment is triggered by presenting findings, not by the committee formally accepting or approving them. In practice, that means 75 percent of the fee is guaranteed once ASBB shows up to the two scheduled meetings, regardless of whether the committee is satisfied with what's presented.
The kickoff meeting told a different story than the paperwork
At the October 14, 2025 kickoff meeting, Warden Penny Smith asked ASBB directly about the schedule she recalled from the proposal: something in the range of 18 to 20 weeks. The consultant's answer, based on the meeting recording, was less certain than the question. It moved from "about 26 weeks altogether" to a correction of "22 weeks," all within the same breath. A few minutes earlier in the same meeting, when asked when the committee wanted the project finished, the consultant had turned the question back around, and the group informally settled on "in line with our project cycle... like March," which works out closer to 20 or 22 weeks from the kickoff date.
None of those numbers, 18, 20, 22, or 26 weeks, were stated with much confidence by anyone in the room, including the people who had written and evaluated the winning proposal.
Where things stand now
The municipality's public project page now lists an anticipated completion date at the end of July 2026. Counting from the October 14 kickoff, that's roughly 41 to 42 weeks, nearly double the most generous figure raised at the kickoff meeting and about four months past the informal March target the committee and consultant landed on that same day.
To be fair, project timelines shift for all kinds of reasonable causes. Nothing in the public record reviewed for this piece explains why this one moved, and the transcript does show the scope growing somewhat organically along the way, with a related archaeological assessment and lidar mapping added to the work plan after the kickoff, plus ongoing coordination with the separate Harts Point property review. Any of those could account for part of the delay. What's missing so far is a public explanation connecting the added scope to the new date.
Why it’s worth asking about
Timeline was weighted as heavily as experience in deciding who got this contract, which suggests the municipality considered it a meaningful part of what it was paying for. When the delivery date moves this far past what was discussed at the outset, without an accompanying update on why, residents lose the ability to judge whether the original scoring held up. That's a fixable gap. A short note on the project page, or a line in a future committee update, explaining what changed and why the new date makes sense, would go a long way toward keeping the process as transparent as the committee has said it wants to be.
None of this is a claim that the work itself is behind or falling short. The market gap analysis hasn't been delivered yet, and it should be judged on its own merits once it is. The timeline, though, is public information that residents were told mattered enough to be scored, and it's reasonable to ask what happened to it.
